Raichur Thermal Power Station

Raichur Thermal Power Station
Location of the Raichur Thermal Power Stationb in Karnataka.
Country India
Location Raichur district, Karnataka.
Coordinates 16°21′18″N 77°20′31″E / 16.35500°N 77.34194°E / 16.35500; 77.34194Coordinates: 16°21′18″N 77°20′31″E / 16.35500°N 77.34194°E / 16.35500; 77.34194
Status Operational
Commission date Unit 1 & 2: 1986
Unit 3 & 4: 1994
Unit 5 & 6: 1999
Unit 7: 2002
Unit 8: 2013
Operator(s) KPCL
Thermal power station
Primary fuel Coal
Power generation
Units operational 7 X 210 MW 1 X 250 MW
Nameplate capacity 1,470 MW

Raichur Thermal Power Station (RTPS) is a coal-fired electric power station located in the Raichur district of the state of Karnataka, India. It is operated by the Karnataka Power Corporation Limited (KPCL) and was the first thermal power plant to be set up in the state.[1][2] The power station was commissioned during various periods from 1985 and it accounts for about 40% of the total electricity generated in Karnataka.[3]

Establishment

The project to construct the thermal power station was finalized in 1978 after an MOU was signed between KPCL and the Karnataka State Electricity Board.[4] TCE Consulting Engineers Ltd., a Tata Group company was appointed as the consultants for the project. The project involved two stages: Stage I, in which Units 1 and 2 were expected to be installed and Stage II, Units 3 and 4. Each unit was expected to have an installed capacity of 210 MW. An area of 300 hectares was allocated for the units. Unit I of the plant was completed in March 1985, with Unit II following in March 1986.[4]

The construction of Unit III was started in 1986 and completed in March 1991 and the Unit IV was started in 1989 and completed in September 1994, thereby completing the Stage II. The total cost of Stage I of the project was Rs. 4,030,000,000 and of the Stage II was Rs. 9,830,000,000. The generators were supplied by Bharat Heavy Electricals Limited and the turbines by Kraftwerk Union AG (KWU) and Mitsubishi. In 1996, a further expansion of the plant was carried out, with an investment of Rs. 15,450,000,000.

Units 5 and 6 (each of 210 MW) were installed within three years.[5] Unit 7 (210 MW) which was completed within a record time of 25 months, was installed at the end of the year 2002[5] The total installed capacity of the power plant is 1,470 MW (7 x 210 MW). As of 2007, Unit 8, with an installed capacity of 250 MW, is being constructed and is expected to be operational by September 2009.[6]

Stage I (units 1 and 2) costing Rs. 403,00,00,000 (Rs. 403 crores or Rs. 4.03 bn) in 1986.

Stage II (units 3 and 4) costing Rs. 983,00,00,000(Rs. 983 crores or Rs. 9.83 bn) in 1994.

Stage III (units 5 and 6) costing Rs. 1545,00,00,000 (Rs. 1545 crores or Rs. 15.45 bn) in 1999.

Stage IV (unit 7) costing Rs. 613,00,00,000 (Rs. 613 crores or Rs. 6.13 bn) in 2002.

Stage IV (unit 8) costing Rs. 945,00,00,000 (Rs. 945 crores or Rs. 9.45 bn) in 2010

Raw materials

RTPS uses coal for generation of electricity. Its daily requirement of coal is about 24,000 metric tons, delivered from Western Coalfields Ltd. and Mahanadi Coalfields Ltd. The coal supplied is sampled using a computerized system and sent to the laboratory for testing. This ensures that the proper grade of coal is used.

The plant has also started to use washed coal, due to its lower ash content.[7]

The plant's cooling water is pumped from the Krishna river nearby.

Electricity production

The coal is pulverised and fed into furnaces that convert water into steam. This steam runs the turbines to generate electricity. Each unit produces about 5 MU per day and hence the plant can produce 35 MU per day when it is functioning at full capacity.[8]

Issues

RTPS generates about 1.5 million tonnes of fly ash annually which causes environmental problems. 20% of the ash produced is wet bottom ash which is let into the ash bund.[8] Though considered safer than fly-ash, bottom ash has also been found to contain heavy metals which can be dangerous to public health. The fly-ash which gets generated during the burning of coal disperses into the air and hence pollutes the atmosphere. This gets deposited on the surrounding land, thereby making the land infertile. The fly-ash may also cause breathing problems for humans. RTPS has taken steps to ensure that fly-ash gets precipitated out of the air by using electrostatic elements in the furnaces, but about 2% of fly-ash gets into the atmosphere.[8] The fly-ash is disposed of by converting it into a wet slurry and dumping it into vacant tracts of land (which become what are known as ash-ponds).[9] This is not environment friendly and hence RTPS has come up with ways to make better use of fly-ash. It has entered into a collaboration with the Indo-Norwegian Environment Programme (INEP) and has set up a technology demonstration centre called CASHUTEC (Centre for ASH UTilisation and Environment Conservation) near its plant.[9] CASHUTEC demonstrates different uses for fly ash; mainly its use in the construction sector for making bricks, blocks and mosaic tiles.[9]

Notes

Wikimedia Commons has media related to Raichur Thermal Power Station.
  1. "Projects of KPCL". Retrieved 2007-10-27.
  2. "More locations identified to set up power plants". Online Edition of The Hindu, dated 2007-03-26. Chennai, India. 2007-03-26. Retrieved 2007-11-01.
  3. "All units of RTPS going full steam". Online Edition of The Hindu, dated 2007-01-07. Chennai, India. 2007-01-07. Retrieved 2007-11-01.
  4. 1 2 "Karnataka Power Corporation Limited, 2 x 210 MW Raichur Themal Power Plant : Stages – I & II" (PDF). Online Webpage of TCE Consulting Engineers Ltd., A TATA Enterprise. Retrieved 2007-11-01.
  5. 1 2 "Raichur Thermal Power Station". Online webpage of KPCL. Retrieved 2007-11-01.
  6. "Raichur Thermal Power Station-Unit 8". Online webpage of KPCL. Retrieved 2007-11-01.
  7. "Coal sampling computerised". Online Edition of The Hindu, dated 2004-01-12. Chennai, India. 2004-01-12. Retrieved 2007-11-01.
  8. 1 2 3 "Guidelines for Hazardous waste, Part I, Recommendations for environmental politics and administration, Introduction of collection and disposal systems under particular consideration of framework conditions in India and Vietnam, Ver 1.0, Oct 2006" (PDF). Sacodi Project. Retrieved 2007-11-01.
  9. 1 2 3 Bharathi Ghanashyam. "Cashing in on fly ash". Online Edition of The Hindu Business Line, dated 2006-08-04. Retrieved 2007-11-01.
This article is issued from Wikipedia - version of the 4/13/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.