Tumarín Dam

Tumarín Dam
Location of Tumarín Dam in Nicaragua
Official name Presa Tumarín
Country Nicaragua
Location Tumarín
Coordinates 13°0′30.79″N 84°24′25.24″W / 13.0085528°N 84.4070111°W / 13.0085528; -84.4070111Coordinates: 13°0′30.79″N 84°24′25.24″W / 13.0085528°N 84.4070111°W / 13.0085528; -84.4070111
Purpose Power
Status Preliminary construction
Construction began 2011
Opening date 2019 est.
Construction cost US$1.1 billion
Dam and spillways
Type of dam Gravity, roller-compacted concrete
Impounds Río Grande de Matagalpa
Height 45 m (148 ft)
Length 350 m (1,150 ft)
Reservoir
Total capacity 200,000,000 m3 (160,000 acre·ft)
Catchment area 15,300 km2 (5,900 sq mi)
Surface area 20 km2 (7.7 sq mi)
Max. water depth 30 m (98 ft)
Power station
Turbines 3 x 84.22 Kaplan-type
Installed capacity 253 MW
Annual generation 1,184 GWh (est.)

The Tumarín Dam is a 60 meter tall, concrete gravity dam planned for construction on the Río Grande de Matagalpa just upstream of the town of Tumarín in the South Caribbean Coast Autonomous Region, Nicaragua. It is located about 35 km (22 mi) east of San Pedro del Norte, where the Río Grande de Matagalpa meets the Tuma River.[1] First announced in March 2010, construction was expected to take four years, but there have been many delays. Preliminary construction (roads, bridges and foundation) was to begin in 2011 and main works were expected to begin in February 2015. Completion is scheduled for 2019.[2] Brazil's Eletrobras will fund the US$1.1 billion under a 20 to 30 year build–operate–transfer (BOT) agreement. The project is being developed by Centrales Hidroelectricas de Nicaragua (CHN).[3] The power station located at the base of the dam will house three 84.33 MW Kaplan turbine-generators for an installed capacity of 253 MW.[4] The dam will create a reservoir covering 40 square kilometers.[5]

References

  1. "Perfil Central Hidroeléctrica Tumarín" (PDF) (in Spanish). Ministerio deEnergía y Minas. Retrieved 29 April 2014.
  2. "Brazilian companies to build a US$1.1 billion dam in Nicaragua as of next February". Trade News. 12 November 2014. Retrieved 22 November 2014.
  3. "Nicaragua set to break ground on 253-MW Tumarin hydroelectric project". Hydro World. 29 January 2014. Retrieved 29 April 2014.
  4. Kaften, Cheryl (24 August 2011). "Mixing Water with Oil: Nicaragua Adds Hydroelectric Capacity to Its Power Portfolio". GreenTechnologyWorld. Retrieved 29 April 2014.
  5. (PDF). European Investment Bank November 2015/Environmental Social Data Sheet http://www.eib.org/infocentre/register/all/63908592.pdf/articles/17 November 2015/Environmental Social Data Sheet Check |url= value (help). Retrieved 26 March 2016. Missing or empty |title= (help)
This article is issued from Wikipedia - version of the 3/26/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.