SunRail

SunRail

A southbound SunRail train leaving Winter Park Station.
Overview
Owner FDOT
Locale Greater Orlando
Transit type Commuter rail
Number of lines 1
Number of stations 12
Daily ridership 3,800 (2015)[1]
Website www.sunrail.com
Operation
Began operation May 1, 2014 (2014-05-01)
Operator(s) Bombardier Technology[2]
Technical
System length 31.7 mi (51.0 km)[3]
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Average speed ~30 mph (48 km/h)
Top speed 65–79 mph (105–127 km/h)

SunRail is a commuter rail system in the Greater Orlando, Florida area. Service began on May 1, 2014.[4] Phase 1 comprises 31 miles (50 km) with 12 stations[4] along the former CSX Transportation "A" Line connecting Volusia County and Orange County through Downtown Orlando. The extensions proposed for Phase 2 would add a new northern terminus at DeLand and four more stations southward, terminating at Poinciana in Osceola County. It is expected to be fully completed sometime in 2017.[5] Formerly known as "Central Florida Commuter Rail", the SunRail system is financed by the state and Federal governments and the counties it serves. SunRail is Florida's second commuter rail system after South Florida's Tri-Rail.

SunRail opened on May 1, 2014 with over 10,000 passengers riding the trains on opening day.[6] In 2015 the system saw 957,800 passenger trips, for an overall average of 3,800 paying riders per weekday.[1]

History

Cost and funding

Instead of building an entirely new rail line, the State of Florida purchased a 61-mile segment of the existing "A" Line between DeLand and Poinciana from CSX Transportation. The total cost of the system was originally estimated at $615 million for construction plus $432 million to purchase the right of way and tracks. However, the cost of construction ended up being above the $615 million quoted and the agreement still allows CSX to run a limited number of freight trains along the line at night, although the majority of the freight traffic has been rerouted west to CSX's "S" Line.[7]

The system was financed by the federal government, the state and the counties. Volusia County, Seminole County, Orange County, the City of Orlando and Osceola County are the partners in the project. Fifty percent of the funding came from a federal transit "New Starts" grant. The local partners were responsible for 25 percent of the cost and another 25 percent was paid by the State of Florida, which included the cost of track improvements, construction of train stations, and purchasing of locomotives and rail cars.

On 22 December 2010, it was announced that the state of Florida had created an escrow account with $173 million.[8] The money was planned to be used to purchase the tracks SunRail operates on, and also allowed the state to formally request $300 million from the federal government to cover construction costs.[8]

During its first year of operation, SunRail made a total of $7.2 million from a combination of fares, advertising and fees paid by CSX and Amtrak to run their trains through the corridor. However, SunRail spent a total of $34.4 million during that same year, ending it with a $27.2 million deficit and an average daily ridership of 3,700 passengers.[9]

Project planning and approvals

Geographic map

At the end of July 2007, Orange County, Seminole County, Osceola County, Volusia County and the City of Orlando all voted on and approved the Sunrail project. Osceola County had agreed in principle, but was still examining how to fund its $9.3-million share at the time.[10][11][11][12][13]

An agreement was reached between Florida Department of Transportation and CSX for the purchase of the tracks on November 29, 2007, and the Florida Legislature approved the CSX-Florida Department of Transportation agreement in order for project construction to begin. However, the legislature failed to vote on the agreement to purchase the right of way and tracks from CSX in the 2008 session. At issue were provisions regarding liability and indemnification. Commenting on the bill, state senator Paula Dockery said, "I don't envision a time anytime soon where thoughtful senators are going to say that there's some kind of good public policy involved in taking liability away from somebody who was at fault and putting it on the taxpayers of the state of Florida."[14]

The contract between CSX and Florida DOT was in place through June 30, 2009, and the legislature planned to use another opportunity to consider and approve the agreement in the 2009 legislative session.[15][16] The bill made it through all necessary Senate committee approvals and the first segment of the project had already been approved to enter Final Design by the Federal Transit Administration on August 11, 2008.

On January 14, 2009, the SunRail name and logo were presented to the public by City of Orlando Mayor Buddy Dyer.[17] Progress continued to move slowly forward on the project until the state legislative session on April 30, 2009, when the project was once again defeated by a 23-17 vote. The movement against the project, which was once again led by state senators Paula Dockery and Mike, continued to revolve around an amendment that would have approved a $200 million insurance policy for SunRail. Another political problem for SunRail was an overall lack of support for the project from the South Florida delegation (which included state senators Chris Smith of Fort Lauderdale, Dan Gelber of Miami Beach, Nan Rich of Weston and Frederica Wilson of Miami) effectively killed the bill.

After the second failure, with the deadline to purchase the tracks in question from CSX looming, the state initially pulled the plan from the legislative agenda, endangering as much as $307 million in federal funds that had been promised to SunRail, which would have been taken away if the plan failed. Nearly $27 million of that federal money had already been spent to purchase rail equipment and land for stations and it was unknown whether or not the State of Florida would have had to pay the money back to the federal government. However, CSX rescinded the deadline on June 29,[18] permitting more negotiation time for insurance arrangements. An agreement on insurance was finally reached, and lawmakers convened a special session in December 2009 that passed the House on December 7 and the Senate on December 8. Additional federal money may be attracted to reduce the financial cost to the state.[19]

On December 8, 2009 the contractual requirement necessary to move forward with SunRail was passed along with funding for South Florida's Tri-Rail system. At the bill's signing Senate President Jeff Atwater said "Today, Florida is embracing the opportunity to lead the nation in developing a comprehensive transportation system, thereby ensuring our competitive edge in the 21st Century global economy. A comprehensive transportation system, creating opportunities and avenues to connect employers and employees, is integral to building a stronger future for Florida."[20]

Negotiations with Amtrak subsequently led to a dispute over which party would bear liability for incidents on Amtrak trains operating on the route, which would be owned by SunRailAmtrak wanted SunRail to assume responsibility for such incidents, while SunRail wanted Amtrak to be liable. The purchase of the trackage from CSX could not be completed until an agreement with Amtrak was reached.[21] On December 10, 2010, it was announced that Amtrak and the state had apparently reached a deal regarding the issue, as Amtrak had dropped its opposition to the sale.[22]

On January 29, 2011, Florida Governor Rick Scott froze all SunRail contracts and ordered a six-month legislative review of the project to determine whether the project was a good investment.[23] However, on July 1, 2011, Florida Department of Transportation Secretary Ananth Prasad announced that Scott had finally approved the project.[24]

Construction

The Phase 1 construction contract was awarded to two primary general contractors; RailWorks Track Systems, Inc. of New York City, who would be responsible for right-of-way and track improvements, and Atlanta-based Archer Western Contractors Ltd., who would be responsible for building the stations.[25] Work would include double tracking the existing line; the installation of new wayside signals; improvements to existing grade crossings; construction of the station platforms, canopies and adjacent parking areas; as well as building of the Operations Control Center and Vehicle Storage & Maintenance Facility at CSX's Rand Yard in Sanford.

Ground was broken at the future Altamonte Springs station site on January 27, 2012, marking the official beginning of construction for Phase 1 of the SunRail project.[26] The first load of steel rail for double tracking the route between Sanford and Longwood was delivered not long after in early 2012. A second set of rails for double tracking the route between North Street in Longwood and Gore Street south of Downtown Orlando was delivered at the end of March 2012, and a third set, which supplemented various locations between Sanford and Orlando, was delivered at the end of July 2012.[27][28] The sections of standard 115-pounds-per-yard rail were 1650 feet long, weighing 31 tons each.[28] On September 28, 2012, the St. Johns River drawbridge in Sanford was closed for 54 hours while construction crews demolished and replaced the bridge approach spans.[29] By the time Phase 1 construction was completed in early 2014, nearly 32 miles of main line single track were double-tracked, three existing CSX freight yards were reconfigured, wayside signal and grade crossing signal improvements were made along the corridor, a total of 12 stations were built, and a new Operations Control Center and Vehicle Storage & Maintenance Facility were constructed.

Service

Route

The route is made up of the following stations, from north to south:

Town Station Phase Connections Notes
DeLand DeLand Amtrak Station 2 North Amtrak Silver Service, Thruway Motorcoach, Proposed VOTRAN Park-and-ride
DeBary DeBary Station 1 VOTRAN Routes 31, 32, 33 Park-and-ride
Sanford Sanford Station 1 Link 34, Link 46E, Link 46W, NeighborLink 651 Park-and-ride
Lake Mary Lake Mary Station 1 Link 45 Park-and-ride
Longwood Longwood Station 1 Link 434(at SR434 and Ronald Reagan Blvd. Direct Service to station discontinued 12/11/14) Park-and-ride
Altamonte Springs Altamonte Springs Station 1 Link 436N Park-and-ride
Maitland Maitland Station 1 Link 102, Neighborlink 652 Park-and-ride
Winter Park Winter Park Station 1 Amtrak Silver Service,Link 1, Link 9, Link 14, Link 23, Link 102, Link 443
Orlando Florida Hospital Health Village Station 1 Link 102, Link 125 Florida Hospital
Lynx Central Station 1 Link 3, 7, 8, 11, 13,15, 18, 20, 21, 25, 28, 29, 36, 38, 40, 48, 49, 50, 51, 54, 102, 104, 105, 106, 107, 125,300, 304, 313, 319, FastLink 406, FastLink 441,Lymmo Orange Line-Downtown, Lymmo Lime Line
Church Street Station 1 Lymmo - Orange Line-Downtown and Grapefruit Line near Amway Center
Orlando Health/Amtrak Station 1 Amtrak Silver Service, Link 40, Thruway Motorcoach Orlando Regional Medical Center
Orlando International Airport Station 3 Automated People Mover (APM) to airport terminal, Brightline, Orlando Maglev, Link 11, 42, 51, 111, 436S, FastLink 407 South Airport Intermodal Terminal
Pine Castle Sand Lake Road Station 1 Link 11, 18, 42, 111,Xpress Link 208,FastLink 418 Park-and-ride
Meadow Woods Meadow Woods Station 2 South Link 18, FastLink 418 Park-and-ride
Hunter's Creek Tupperware Station 2 South Link 18, Neighborlink 631 Park-and-ride
Kissimmee Kissimmee Amtrak Station 2 South Amtrak Silver Service, Link 10,18,26,55,56.57,108,Xpress Link 208,FastLink 441,and Neighborlink 632 at Lynx Kissimmee Multimodal Center, Greyhound Park-and-ride
Poinciana Poinciana Station 2 South Link 306 Park-and-ride

Schedule

SunRail runs on weekdays excluding holidays in the daytime and on weekends if a sponsor pays to keep the service open, for instance sports or festival organisers.[30] SunRail says it would cost $19 million to obtain the additional trains and $10 million in additional operating costs to expand into weekend services, and increase the number of daily rides from 34 to 40.[31]

SunRail curtailed late night train service on 21st December 2015 citing ridership. A mid-day train to service leisure riders was introduced.[32]

SunRail considered testing a Saturday train schedule. The test would be from November 2016 to January 2017 and is being led by several major businesses including the Downtown Orlando Partnership and Downtown Development Board. Money for this test would be supplied by local businesses in the same way crowd funding is used: each company involved will give money towards the operating expenses in exchange for on-train advertising, logo placement on stations and billboards, and social media promotions. [33] [34] Weekend trains will run between afternoon and evenings and are adjusted to serve specific events. The cost of running trains on Saturday is about $20,000. [35] This service was to start in November 5th.[36]

Fare system and ticketing

Riders on the SunRail system use a Stored-value card, in the form of a disposable Limited Use Ticket or a Reloadable SunCard, to pay fares. The cost of SunRail tickets is based on the number of counties (zones) through which the rider will be travelling. As of 2014, the system passes through three counties: Volusia; Seminole; and Orange. In Phase 2, the system will also enter Osceola.[37][38]

SunRail uses a "tap on/tap off" system for ticketing. Riders must "tap on" at a validator unit at the station prior to boarding the train by tapping their ticket on the screen and waiting for the beep. Riders must again "tap off" at a validator unit with their ticket after disembarking at their destination before exiting the station. Reduced Fares are available for Disabled, Seniors (65+), and Students (7-17).[39]

Limited Use Tickets

Every station on the line is equipped with ticket vending machines. These machines sell Limited Use Tickets for one-way trips and round-trips. They are also used by riders making a transfer from a Lynx or Votran feeder buses to swipe a transfer card and to obtain a SunRail ticket.[39]

Reloadable SunCards

Reloadable SunCards are also available at station vending machines. These cards can hold a travel plan and be used as a prepaid debit card. Travel plans are available in 7 day, 30 day, and 1 year timeframes.[39]

Technical

An MPI MP32PH-Q locomotive in SunRail livery in September 2013.

Operations and maintenance

In addition to SunRail commuter trains, the line is used by three daily round trip Amtrak trains (the Silver Meteor, the Silver Star and Auto Train), as well as by a handful of CSX freight trains. It was also used by Amtrak's tri-weekly Sunset Limited which ran between Orlando and Los Angeles. However, service has been suspended indefinitely between Orlando and New Orleans since 2005 due to damage caused to the line by Hurricane Katrina.

The Florida Department of Transportation announced on April 16, 2013 that it had awarded Bombardier Technology a $195 million contract to provide operation and maintenance services for SunRail, which includes train operations, dispatching, track and equipment maintenance, customer service, station platform & facility maintenance, and materials supply. Bombardier assumed the operations and maintenance responsibilities in the spring of 2014.[2]

On Monday, July 29, 2013 at 3:30 AM, the Florida Department of Transportation assumed all train dispatching duties along the SunRail corridor from CSX. This event officially marked the end of CSX's involvement with the operations of the line, transferring total operational control of the corridor to the State of Florida. Since the hand off from CSX, all train dispatching has been handled by the CFRC Dispatcher out of the Operations Control Center at Rand Yard in Sanford, Florida.

Operational testing of the SunRail equipment began on October 26, 2013 along the corridor between the DeBary and Maitland stations. The test train, which consisted of a locomotive and two cab cars, was part of a 2,500 mile "burn-in" period that is required prior to the start of revenue service. Over 100 similar test runs took place over the following months to ensure that the new trains, wayside signals and grade crossing signals operated correctly, as well as to verify that the trains properly aligned with each station platform.[40]

On Friday, January 31, 2014, the Florida Department of Transportation announced that SunRail would begin service on May 1, 2014.[41] SunRail initially offered a series of free test runs in April,[42] but canceled them and instead decided to open for free for the first two weeks of service in May. This enabled remaining work to be completed in time. SunRail warned passengers who already purchased fare cards not to use their fare cards during the free run, or they may be deducted fares.[43]

The SunRail grand opening was held at the Sand Lake Station at 11:00am EDT on Wednesday, April 30, 2014. This was preceded by a series of openings at the other stations, starting at the DeBary Station at 8:15am EDT, and progressing south down the line through the other stations at 15 minute intervals.[44] Passenger operations officially commenced on Thursday, May 1, 2014 with the first revenue service train departing south out of the Sanford Station at 5:06am EDT.[45] Sunrail trains operate at speeds between 30 and 79 miles per hour (48 and 127 km/h), with an average speed of 33 miles per hour (53 km/h), including stops.[46]

All SunRail operations and maintenance personnel are employees of Bombardier Transportation. Approximately 24 engineers and conductors are on the operating roster at any given time. SunRail train crews (engineers & conductors) are represented by the American Train Dispatchers Association (AFL/CIO) labor union.

Rolling stock

Sunrail trains operate at speeds between 30 and 79 miles per hour (48 and 127 km/h), with an average speed of 33 miles per hour (53 km/h), including stops.[46] Each car is fully wheelchair accessible and equipped with a restroom, space for bicycles, electrical outlets for laptops and phone chargers, and free Wi-Fi.[47] In 2011 the Florida Department of Transportation ordered fourteen BiLevel coaches from Bombardier Transportation for $41 million, with an option for 46 additional cars.[48] This order was later expanded to twenty, with the first cars arriving in Florida on July 20, 2013.[49] MotivePower Industries supplied seven MPI MP32PH-Q diesel locomotives. These were ordered on September 12, 2011.[50] The first locomotive, #100, arrived on October 1, 2013 via CSX freight train at the SunRail Operations Control Center in Sanford, FL from the MotivePower plant in Boise, Idaho.[51]

Photo Year Make Model Numbers Total Horsepower Weight Seats Notes
2013 MPI MP32PH-Q 100-109 10 units 3,200 285,000 to 295,000 lb (129,000 to 134,000 kg) (3 crew)
  • Order placed on September 12, 2011.[50]
  • 100 was the first unit to be arrive, it was delivered on October 1, 2013 by CSX to the SunRail Operations Control Center in Sanford, FL.
2012–13 Bombardier BiLevel 2000–2012 (13 cab cars)
3000–3006 (7 trailer cars)
20 units N/A 110,000 lb (50,000 kg) 136 (3 crew)(cab cars)
142 (trailer cars)
  • Order placed in 2011
  • First units Delivered on July 20, 2013.[49]
  • 14 units were initially ordered, with an option for 46 additional units, order later expanded to 20 units.[48]
  • All units are wheelchair accessible and equipped with restrooms, space for bicycles, electrical outlets, and free Wi-Fi.[47]

Paint scheme

On September 10, 2010, the Central Florida Commuter Rail Commission chose a paint scheme for the trains.[52] The design featured a sun along with renderings of green for wildlife and blue for skies.[52] According to the designer, Jim Bockstall, the scheme was based on public input and was intended to include both movement and traditional imagery.[52]

Safety and security

Safety features at stations include bells, gates, and LED displays

In the months leading up to SunRail going operational, the Florida Department of Transportation (FDOT) ran an aggressive public-safety campaign to warn drivers and passengers about railroad safety[53] using pamphlets, puppet shows for children, YouTube[54] and even a Safety Mascot Squirrel named Tie.[55] Despite this effort, SunRail has experienced several accidents with both motorists and pedestrians. Nearly a year into service, officials began installing dial-up grade crossing systems at grade crossings that are located closest to the stations. This system allows train crews to manually activate grade crossing warning devices (i.e. crossing gates, lights and bells) from the locomotive cab via key-coded radio transmission, thus eliminating the confusion of the grade crossing warning devices automatically activating, deactivating and reactivating whenever trains approach, stop at and depart the stations.[56]

Security on the train and at stations is the responsibility of FDOT. The FDOT does not employ a security force and relies solely on surveillance cameras and emergency call boxes.[57] Uniformed police officers are permitted to ride SunRail free of charge.[58]

Grade crossing accidents

Because of the flat terrain and high water table of the Orlando area, the entire route of SunRail is at grade. Most road crossings except for expressways are not grade-separated; even major arterials like Route 17/92 have level crossings in populated areas. There are 96 grade crossings along the Phase 1 route, with an additional 30 on Phase 2.[59][60] SunRail dramatically increased frequencies on the line, with 34 daily trips. Six daily Amtrak trains (three round trips) continue to operate, while 20 daily freights have largely been moved to the CSX "S" Line to the west.[61]

Within the first five months of regular operations, SunRail trains were involved in four grade crossing accidents, all caused by driver error. Florida Highway Patrol officials blamed the crashes on drivers who were too impatient to wait for trains to pass and did not understand that trains cannot stop quickly.[61] Tri-Rail, which operates in a very similar densely populated area with many grade crossings, had 93 crashes during its first 15 years, though other systems saw their rates decrease after the initial months.[61] After two more driver-caused accidents in early 2013, police increased enforcement of drivers bypassing crossing gates in an attempt to prevent additional crashes.[62]

Due to an accident on October 8, 2015, where a dump truck was parked too close to the tracks and was side-swiped by a train, the Florida Highway Patrol has begun monitoring crossings and station areas. Billboards and mailers about train safety will also be put out to raise awareness. As of this accident, all incidents involving vehicles and SunRail trains have been the fault of the vehicle driver.[63]

Plans and expansions

Looking north from the DeBary station; SunRail plans to expand north to DeLand from here

Phase 2

SunRail divided their startup operations into two phases. Phase 1 opened on May 1, 2014 between DeBary and Sand Lake Road. Due to budgetary constrains, Phase 2 will be constructed and opened in two separate segments; Phase 2 South and Phase 2 North. Because federal funding in the amount of $93 million[64] has already been secured for Phase 2 South, construction on this segment will begin first. This segment will extend the system 17 miles south from Sand Lake Road into Osceola County with a stop at the existing Kissimmee Amtrak station as well as new stations being built in Meadow Woods, Hunter's Creek and Poinciana. Phase 2 North will eventually extend the system 13 miles north from DeBary to the existing DeLand Amtrak station. However, the additional $35 million in federal funding needed to develop Phase 2 North still has yet to be secured.

On August 14, 2015, the State of Florida received the full funding grant agreement from the Federal Transit Administration that moved forward completion of SunRail Phase 2 South. Congressman John Mica stated that because of the expedited agreement, full funding for the additional 17-mile extension was expected to be approved by the end of September.[65] On September 28, 2015, the $93 million grant was formally approved at a ceremony at the Kissimmee Amtrak station.[66] With matching state and local funding already in place providing an additional $93 million, construction on Phase 2 South is now planned to begin in early January 2016,[67] with service on the route expected to begin in December 2017.[66] But the Florida Department of Transportation announced Wednesday, February 17th, that construction delays will likely push the expansion opening to the first quarter of 2018, though the delay will not cost Osceola County anything additional.[68] Work was expected to begin in December 2015, but the Florida Department of Transportation delayed the selection of a design/build team until October 26, 2015, thus pushing back the start date by approximately a month.[67]

Despite the delay in starting construction on Phase 2 South, the City of Kissimmee broke ground at the end of October 2015 on a parking structure next to the proposed Kissimmee SunRail Station and existing Multimodal Center, which is used by the Lynx and Greyhound bus services. The parking structure will be 4 stories, accommodate 400 cars, and will have an expected $10.1 million price tag.[69] It was also announced that Tupperware Brands Corporation added an extra $120,000 for upgrades to the Hunter's Creek Station, which will be built on land near their headquarters. This was done in exchange for naming rights to the station, which is now called the Tupperware Station. This funding will be used for additional landscaping and lighting along with cosmetic upgrades to the station design so that it will mimic the Tupperware headquarters building.[70]

On October 29, 2015, SunRail officials were denied a $35 million federal grant for the 13 mile Phase 2 North extension to Deland in Volusia County due to low ridership projections. County and SunRail officials were counting on this money to help pay for half of the $70 million cost to build this extension.[71] In wake of not receiving federal funding, an additional station in Orange City is now being considered to boost ridership projections along the Phase 2 North extension.[72]

Congressman John Mica announced on November 25th, 2015 that $63 million in federal dollars were on the way to assist the completion of Phase 2 South.[73] On March 28th, 2016, the Florida Department of Transportation gave notice that Phase 2 South construction would begin on April 1st, 2016 with service expected to begin by February 2018. A construction commencement ceremony took place on April 25, 2016 at 10:00 AM at the site of the future Tupperware Station, which officially kicked off construction.[74]

The Florida Department of Transportation said on May 3rd, 2016, that the northern extension of SunRail to DeLand has been halted due to the inability to obtain the necessary funds. The cost of this extension is estimated at $77 million, with half paid by grants and the other half by the FDOT. They have said they will continue to look for funding for the Phase 2 northern extension. [75]

The Dana B. Kenyon Company based in Jacksonville, FL, has been awarded the $31.7 million contract for the Phase 2 southern extension project. This includes many aspects at each of the 4 new stations, as well as new vehicle storage and maintenance facilities. [76]

Phase 3 (Airport Connection)

SunRail officials are currently investigating a Phase 3 expansion, which would include a connection to Orlando International Airport.[77][78] Currently this connection requires transferring to a shuttle bus at Sand Lake Road Station. The 5.5 mile route currently under consideration would travel 3.5 miles along an existing Orlando Utilities Commission (OUC) rail spur, which runs along the southern boundary of the airport's property and is used exclusively by coal trains to serve the Curtis H. Stanton Energy Center in eastern Orange County. From there, two options are currently under consideration; one plan would have SunRail trains branch north off of the existing OUC line and onto a new 2-mile spur that would terminate at the planned South Airport Intermodal Terminal. The second option being explored would be to build a transfer station along the OUC line where passengers would transfer from SunRail trains onto light rail trains that would run along a dedicated 2-mile line between the transfer and airport stations.[77][79] Once at the South Airport Intermodal Terminal, passengers would transfer onto an Automated People Mover (APM) that would take them the 1.5 mile distance north to the existing airport terminal. Passengers would also be able to transfer directly to Brightline trains, a planned privately funded higher speed rail passenger service of the Florida East Coast Railway, which would offer sixteen daily roundtrips to Miami[80] starting in 2017.[77][81][82] Direct transfers would also be available to one of two proposed alternatives; either a Maglev train or a light rail train, both of which are planned to run between the South Airport Intermodal Terminal and International Drive.[83][84] The cost of the Phase 3 expansion is currently estimated at $225 million.

In September 2015, SunRail officials submitted a request to the Federal Transit Administration (FTA) to move the project from the initial planning phase into the project development phase, which it approved on October 26, 2015.[85]

Daytona Beach extension

On April 17, 2014, Volusia County and FDOT funded a $2.5 million study to investigate the cost, preliminary design and ridership of a SunRail extension to Daytona Beach. As part of this effort, Volusia County wants to see the Interstate 4 median width maintained as a possible future rail corridor.[86]

See also

References

  1. 1 2 "Transit Ridership Report: Fourth Quarter 2015" (PDF). American Public Transportation Association. 2 March 2016. Retrieved 29 April 2016.
  2. 1 2 "Florida DOT awards $195 million SunRail contract to Bombardier". Progressive Railroading. 2013-04-16.
  3. Google (15 May 2014). "SunRail - Central Florida Commuter Rail" (Map). Google Maps. Google. Retrieved 15 May 2014.
  4. 1 2 "Free SunRail rides start Thursday". orlandosentinel.com. Orlando Sentinel. Retrieved 2 May 2014.
  5. "SunRail Phas II South : Orlando, Flrida" (PDF). Fta.dot.gov. Retrieved 2015-03-03.
  6. "10,000 pack SunRail on opening day, causing delays". Orlando Sentinel. Retrieved 2015-03-03.
  7. "FDOT, CSX Transportation Execute Commuter Rail Agreement". Florida Department of Transportation. 30 November 2007. Retrieved 23 July 2011.
  8. 1 2 "SunRail's $173 million escrow account moves commuter rail one step closer to construction phase". Orlando Sentinel. 22 December 2010. Retrieved 23 December 2010.
  9. "SunRail finishes first year $27.2 million in the red". Orlando Sentinel. 10 May 2015. Retrieved 12 May 2015.
  10. "First commuter rail vote happens Thursday". Central Florida News 13 (online). 19 July 2007. Archived from the original on September 27, 2007.
  11. 1 2 "Orlando on board for rail". OrlandoSentinel.com. 2007-07-24. Retrieved 2010-12-23.
  12. "Commuter rail votes chug along". Central Florida News 13 (online). 24 July 2007. Archived from the original on September 27, 2007.
  13. "Volusia County Council Actions - JULY 31, 2007". Volusia.org. 2007-07-31. Retrieved 2010-12-23.
  14. "CSX RAILROAD WANTS TO BE TREATED LIKE A KING". The Injury Board. 3 May 2008. Retrieved 21 August 2010.
  15. Miller, James (May 1, 2008). "Senate applies brakes to commuter rail". Daytona Beach News-Journal. Retrieved 2008-05-02.
  16. "State won't buy CSX track in Central Florida". Tampa Bay Business Journal. May 6, 2008. Retrieved 2008-05-06.
  17. Schlueb, Mark (January 14, 2009). "Logo for proposed commuter rail unveiled". Orlando Sentinel. Retrieved 2009-01-14.
  18. "Sentinel exclusive: Commuter-rail plan might be back". Orlando Sentinel. 2009-06-26. Retrieved 2010-12-23.
  19. "Dyer: 3rd time will be charm for SunRail". Orlando Sentinel. 2009-07-02. Retrieved 2010-12-23.
  20. Governor's Press Office, 16 December 2009
  21. "Amtrak dispute could delay SunRail plans". Trains Magazine. 19 August 2010. Retrieved 21 August 2010.
  22. "Amtrak, Florida reach SunRail deal". Trains Magazine. 10 December 2010. Retrieved 15 December 2010.
  23. "Scott Freezes SunRail Contracts for Review". WCTV. Associated Press. 29 January 2011. Retrieved 23 July 2011.
  24. "SunRail gets go-ahead". Gulf Coast Business Review. 1 July 2011. Retrieved 23 July 2011.
  25. "FDOT Awards First SunRail Construction Contract". Business.sunrail.com. Retrieved 2015-03-03.
  26. "SunRail project breaks ground". Railway track and Structures. 27 January 2012. Retrieved 31 January 2012.
  27. "SunRail tracks delivered in Longwood". Orlando Sentinel. 2012-03-22. Retrieved 2012-04-09.
  28. 1 2 "Delivery of SunRail track Monday will cause delays on Sanford streets". Sandford Herald. 30 July 2012. Retrieved 30 July 2012.
  29. "SunRail work to close St. Johns bridge". Orlando Sentinel. 2012-09-26. Retrieved 2012-10-05.
  30. "Train Schedule". SunRail.com.
  31. Tracy, Dan. "SunRail night train service to last at least 1 year". The Orlando Sentinel. Retrieved 2015-04-14.
  32. Tracey, Dan. "Say goodbye to the SunRail late-night train". Retrieved 5 November 2015.
  33. http://www.orlandosentinel.com/news/sunrail/os-sunrail-saturday-20160926-story.html. Missing or empty |title= (help)
  34. http://www.bizjournals.com/orlando/news/2016/09/26/sunrail-to-offer-temporary-saturday-service.html. Missing or empty |title= (help)
  35. http://www.orlandosentinel.com/news/orange/os-sunrail-saturday-service-20160928-story.html. Missing or empty |title= (help)
  36. http://www.orlandosentinel.com/news/orange/os-sunrail-saturday-service-special-events-20161014-story.html. Missing or empty |title= (help)
  37. "A Better Way To Go". SunRail. Retrieved 2015-03-03.
  38. Mike Synan. "Sunrail fares proposed - FOX 35 News Orlando". Myfoxorlando.com. Retrieved 2015-03-03.
  39. 1 2 3 "SunRail - A Better Way To Go". SunRail. Retrieved 14 November 2014.
  40. "SunRail Train Scheduled to Roll - Without Passengers - on Saturday". News-journalonline.com. 2013-10-24. Retrieved 2015-03-03.
  41. "SunRail to start operations on May 1". 2014-01-31.
  42. "SunRail to offer free rides in mid April". Orlando Sentinel. 2014-03-11. Retrieved 2015-03-03.
  43. "Ride SunRail free for first 2 weeks of May". Orlando Sentinel. 2014-04-01. Retrieved 2015-03-03.
  44. Cunningham, Tasha. "SunRail Grand Opening Celebration". http://sunrail.com. SunRail. Retrieved 10 November 2015. External link in |website= (help)
  45. "1st passengers board SunRail". Orlandosentinel.com. 2014-05-01. Retrieved 2015-03-03.
  46. 1 2 Lafferty, Mike (May 21, 2014). "Guess how fast SunRail trains go". Orlando Sentinel. Archived from the original on September 7, 2014.
  47. 1 2 "Passenger Experience". Sunrail. Archived from the original on September 7, 2014.
  48. 1 2 "Bombardier Marks 14th North American BiLevel Rail Car Customer with Orlando-area Project" (Press release). 22 July 2011. Retrieved 11 October 2013.
  49. 1 2 Fluker, Anjali (July 31, 2013). "They're here! First SunRail cab car arrives in Sanford". Orlando Business Journal. Archived from the original on September 7, 2014. Retrieved August 1, 2013.
  50. 1 2 "SunRail, Sound Transit order MotivePower locomotives". Trains Magazine. September 12, 2011. Retrieved September 13, 2011.
  51. "Tweet shows new SunRail locomotive - Commuter rail service set for spring start in Orlando area". WKMG. October 1, 2013. Retrieved February 20, 2014.
  52. 1 2 3 "Rail Commission picks SunRail train design". 10 September 2010. Archived from the original on November 30, 2010. Retrieved 15 December 2010.
  53. Curtis, Henry Pierson (22 May 2014). "SunRail crash video released". Orlando Sentinel. Retrieved 3 March 2015.
  54. "Ride SunRail". YouTube. Retrieved 2015-03-03.
  55. Sturgeon, Marjorie (7 September 2013). "Squirrel picked as SunRail safety mascot". Bay News 9. Archived from the original on 4 December 2013. Retrieved 27 March 2015.
  56. "Crossing arms may be operated inside SunRail trains". ClickOrlando.com. 2015-04-22. Retrieved 2015-05-05.
  57. "Is SunRail safe with no security force? | Local News - WESH Home". Wesh.com. 2014-04-29. Retrieved 2015-03-03.
  58. Synan, Mike (13 February 2014). "Could Charlotte's light rail offer a glimpse of what SunRail will be?". WOFL. Archived from the original on 12 August 2014. Retrieved 12 August 2014.
  59. "PHASE 2 CONSTRUCTION". Florida Department of Transportation. 2015. Retrieved 20 July 2015.
  60. "Sunrail Construction Commences North From Orlando". Eastern Railroad News. 22 May 2012. Retrieved 20 July 2015.
  61. 1 2 3 Tracy, Dan; Powers, Scott (28 September 2014). "SunRail accident-prone during first 5 months". Orlando Sentinel. Retrieved 28 July 2015.
  62. Hush, Chris (27 March 2015). "Officers to increase enforcement at railroad crossings after sixth SunRail crash". WESH Orlando. Retrieved 28 July 2015.
  63. Orozco, Jackie. "SunRail to launch new safety campaign". Retrieved 22 October 2015.
  64. "SunRail gets $93 million to expand into Osceola". The Orlando Sentinel.
  65. Barth, Cindy. "Congress gets SunRail Phase 2 South agreement for review". Orlando Business Journal. Retrieved 17 August 2015.
  66. 1 2 "SunRail gets $93 million grant to expand into Osceola County". Orlando Sentinel. September 28, 2015. Retrieved September 19, 2015.
  67. 1 2 "SunRail Phase 2 south construction start delayed". Retrieved 21 October 2015.
  68. "FDOT: SunRail likely won't arrive until 2018". Retrieved 18 February 2016.
  69. Fluker, Anjali. "SunRail Phase 2 south construction start delayed". Retrieved 24 October 2015.
  70. Synan, Mike. "Tupperware to pay for SunRail station upgrades". Retrieved 15 October 2015.
  71. Tracey, Dan. "Feds nix money for SunRail stop in DeLand". Retrieved 30 October 2015.
  72. Saul, Saenz (2 November 2015). "SunRail leaders consider new station in Orange City". News 13. Retrieved 4 November 2015.
  73. "Federal Dollars Arrive For SunRail Expansion". Retrieved 26 November 2015.
  74. Stephanie Bechara (25 April 2016). "SunRail breaks ground on Osceola expansion". Central Florida News 13.
  75. "SunRail will not be extended to DeLand". Retrieved 25 July 2016.
  76. "Jacksonville company lands Central Florida Sunrail contract". Retrieved 25 July 2016.
  77. 1 2 3 "SunRail will not link with Orlando International Airport for five or more years - Orlando Sentinel". Articles.orlandosentinel.com. 2013-11-16. Retrieved 2015-03-03.
  78. "SunRail takes steps on plans for Phase 3 to Orlando airport". Orlando Business Journal. 2015-09-28. Retrieved 2015-09-30.
  79. "SunRail link to Orlando airport gets closer look". Orlando Sentinel. 2015-10-30. Retrieved 2015-11-05.
  80. "All Aboard Florida Fact Sheet" (PDF). All Aboard Florida. Retrieved 2015-03-27.
  81. "FAQs". All Aboard Florida. Retrieved 2015-03-03.
  82. "Work begins — finally — on Miami-to-Orlando fast train | Miami Herald Miami Herald". Miamiherald.com. 2014-08-25. Retrieved 2015-03-03.
  83. "Maglev-train plan for airport, convention center back on track". Orlando Sentinel. 2015-03-05. Retrieved 2015-05-05.
  84. "Orlando airport board opts to pursue right-of-way". Orlando Sentinel. 2015-12-09. Retrieved 2016-04-01.
  85. "SunRail connector to Orlando airport gets federal OK". Orlando Business Journal. 2015-10-26. Retrieved 2015-10-27.
  86. "Volusia supports $2.5M study of SunRail to Daytona". News-JournalOnline.com. 2014-04-17. Retrieved 2015-03-03.

Route map: Bing / Google

KML is from Wikidata
Wikimedia Commons has media related to SunRail.
This article is issued from Wikipedia - version of the 11/5/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.